Fairfax County moves to find out why approved housing isn't getting built
Supervisors estimate tens of thousands of approved homes sit unbuilt in Fairfax County, and the board wants staff to help get them moving.

The Fairfax County Board of Supervisors on Tuesday told county staff to look for ways to help developers whose housing projects have county approval but haven’t been built, FFXnow reported.
Nobody has an exact count yet. Springfield District Supervisor Pat Herrity estimated there are “at least 40,000” approved homes waiting. Hunter Mill District Supervisor Walter Alcorn estimated 15,000 in Reston and other parts of his district alone. County staff are working on an official tally.
What the county can change
Board Chair Jeff McKay, who brought the proposal with Vice Chair Kathy Smith of the Sully District, said many of the reasons projects stall are “outside our control,” pointing to elevated interest rates and higher construction costs. The board matter asks staff to find where the county can “influence what is in our control.”
Two areas stood out. When a developer needs to change the proffer agreement it reached with the county, the request has to go back to the board, and several supervisors said that process could move faster. “This process could be more streamlined,” Alcorn said.
The second is building permits. Today a permit expires if construction doesn’t start within six months. The package adopted Tuesday asks building officials to grant extensions “when it makes sense and can advance housing construction.”
Staff will also contact developers directly to ask what is holding up their projects. The board’s auditor is running a broader survey of the causes, with a report expected early next year.
What it means for buyers and renters
Approved but unbuilt homes are supply that already cleared the hardest local step, zoning, and still isn’t reaching the market. Financing is part of the story McKay described: Freddie Mac’s weekly survey put the average 30-year fixed mortgage rate at 7.28% on Thursday, up from 7.11% last week and 6.26% a year ago. Higher borrowing costs weigh on both buyers and the builders who finance construction. (More on this week’s rate jump.)
One example: the vacant office building at 1831 Wiehle Avenue in Reston, a site approved for mixed-use residential redevelopment.
The pipeline keeps growing. At the same Tuesday meeting, supervisors approved up to 1,042 homes at Reston’s Lake Fairfax Business Center.