Maryland weighs restarting American Legion Bridge replacement and 6.5-mile Beltway widening

A state memo revives the stalled plan to rebuild the 1962 bridge, possibly with a private partner, on a smaller footprint.

By Closing DMV Staff ·

The American Legion Memorial Bridge seen from the south bank of the Potomac River, its concrete piers reflected in the water
Photo: Famartin / Wikimedia Commons, CC BY-SA 4.0

Maryland transportation officials are considering restarting the stalled plan to replace the American Legion Bridge and widen part of the Capital Beltway in Montgomery County, Maryland Matters reported Tuesday, citing an internal Maryland Department of Transportation memo. Officials confirmed the memo is authentic and said no decision has been made.

One option under consideration is a new public-private partnership, the same kind of deal that collapsed three years ago.

A smaller plan, still billions

The project dates to the 2019 Capital Beltway Accord between Maryland and Virginia. Under Gov. Larry Hogan, Maryland proposed a $7.6 billion plan to add toll lanes along 15 miles of the Beltway and I-270, including the bridge. After Gov. Wes Moore took office in 2023, his administration questioned what the state would get from the deal, and the private partner, Transurban, withdrew.

The memo describes a “more truncated” version: a 6.5-mile stretch of the Beltway up to the I-270 spur. Officials say it would still cost billions. The state’s annual transportation plan sets aside $60 million for early work, and Maryland has applied for $864 million in federal bridge money for eight Beltway spans, including the American Legion Bridge.

The draft timeline calls for meetings with potential builders as soon as the end of 2026, applications in early 2027, a partner chosen by the Board of Public Works in mid-to-late 2027, and a financial close by early 2029.

Transportation Secretary Katie Thomson stressed that a public-private partnership is not the only financing option and said she wants more predictable funding for the Transportation Trust Fund. Transportation advocate Gary V. Hodge said the state has no money for any of these projects in its capital fund.

Why it matters for commuters and neighbors

The bridge opened in 1962 and is at or near the end of its useful life, state officials say. It carries nearly 250,000 vehicles a day with about 12 hours of congestion daily. State Highway Administrator Will Pines said it is considered the state’s worst bottleneck for freight mobility. The stretch recorded about 1,000 crashes over three years, a third of them with injuries or deaths.

The Virginia side has already moved. Virginia’s I-495 Express Lanes extension through McLean opened in November 2025, FFXnow reported, and federal highway officials have publicly pressed Maryland to act. Federal Highway Administrator Sean McMaster said last December that “Governor Moore’s lack of action on the American Legion Bridge corridor is holding back progress.”

For people in Potomac, Bethesda, McLean and Great Falls, the bridge sets daily commute times between the two states. Under the draft timeline, financing would not close until early 2029, so construction is still years away.

Sources: Maryland Matters, FFXnow, Maryland Department of Transportation, Wikimedia Commons: American Legion Memorial Bridge photo (Famartin, CC BY-SA 4.0)

Know something we should cover? Send us a tip. Follow @closingdmv for DMV news.